Updated January 15, 2009

Status of Service Change Implementation Date

Not all of the bus service changes that were approved in December 2008 will be implemented in March 2009, as originally planned. The bus service changes that WILL go into effect in March 2009, include changes to Routes 8, 9, 60 and 75. The planned changes to Routes 10 and 80 will be delayed until early June 2009. Read the Dec. 12 Transportation Committe Staff Report.

GOLDEN GATE TRANSIT SERVICE MODIFICATIONS APPROVED

Next Steps

February-June 2009: Trip Planning Workshops (dates to be announced)

March 2009: Implementation of Changes to Routes 8, 9, 60 and 75

June 2009: Implementation of Changes to Routes 10 and 80

Actions Taken To Date

December 19: Proposal approved by Board of Directors

December 12: Staff report to Transportation Committee (Read the Dec. 12 Transportation Committee Staff Report)

November 21: Public Hearing held on the proposal

November 2008: Five Community Workshops were held in Marin and Sonoma Counties and in San Francisco

October 23, 2008: Proposal presented to Transportation Committee (Read the Oct. 23 Transportation Committee Staff Report)

October 24, 2008: Board of Directors approved setting a Public Hearing.