Posted August 31, 2011 @ 1 pm GOLDEN GATE BRIDGE WEST SIDEWALK WORK COMPLETED EARLY, WEST SIDEWALK REOPENS TO BICYCLISTS @ SUNRISE SEPTEMBER 10SEPTEMBER 13, SEISMIC RETROFIT WORK CLOSES PORTION
|
||
Roof portion of the North > Anchorage Housing. > > This is the part of the WEST > sidewalk that has been closed > since May 31 and will reopen > as of sunrise September 10. > |
![]() |
< 300-foot-long section of the < EAST sidewalk at the < North Anchorage Housing < will be CLOSED for 4 months < for seismic retrofit work, < from Sept. 13, 2011 through < mid-January 2012. |
Golden Gate Bridge Seismic Retrofit Construction Project Overview The Golden Gate Bridge Seismic Retrofit Construction project was divided into three phases, two of which are now completed. Once the seismic retrofit construction is completed, the GGB will be able to withstand a nearby quake of 8.3 magnitude. Phase 1 retrofit the Marin viaduct structures and was completed in December 2001 and Phase 2 undertook the retrofit of the San Francisco viaduct structures and Fort Point arch. It was completed in spring 2008. Phase 3A is a $125 million project that will be completed in 2012. Phase 3A began in April 2008 and retrofits the Marin Anchorage Housing and Pylon N1. The temporary closure of both sidewalks of the Bridge is required as part of the replacement of the roof of the Marin anchorage housing of which the sidewalks are a part. Phase 3B will retrofit the main span, the two main towers, and south tower pier and fender. This final phase is estimated at $260 million and is planned to go out for construction bids in 2013 and take 3.5 years to complete. |
||



