BID(S) RECEIVED

CONTRACT NO. 2012-BT-6
NOVATO BUS FACILITY SECURITY IMPROVEMENTS

BID OPENING: Tuesday, December 20, 2011, at 2:00 p.m.

Bids for the above-referenced Contract were received in the District Secretary’s Office (DSO) and publicly opened in the Board Room, Administration Building, Golden Gate Bridge Toll Plaza, San Francisco, CA, on Tuesday, December 20, 2011, at 2:00 p.m., listed by “Total Bid Price,” beginning with the apparent low Bidder, as follows:

 

BIDDER

TOTAL BID PRICE

   
1.
Massa Construction Co., Inc.
San Rafael, CA
$568,215.00
   
2.
Valentine Corporation
San Rafael, CA

$613,369.00

   
3.
Ghilotti Bros., Inc.
San Rafael, CA
$648,776.90
     
4.

CF Contracting
Fairfax, CA

$791,275.00
Corrected Price
$789,715.00*
     
5. Golden Bay Fence Plus Iron Works, Inc.
Stockton, CA
$861,790.00
     
6. John Pope, Inc.
Fairfax, CA
$909,200.00
   
*Corrected “Total Bid Price” due to arithmetic error.  
     

 

The Bids are currently under review by the District. The Bidders will be notified of the District’s staff recommendation after their review. It is anticipated that the staff recommendation to award Contract No. 2012-BT-6 will be presented to the Building and Operating Committee for review at its meeting of Thursday, January 26, 2011, beginning at 10:00 a.m. The Committee’s recommendation will be forwarded to the Board of Directors for approval at its meeting of Friday, January 27, 2011, beginning at 10:00 a.m. Both meetings will take place in the Board Room, Administration Building, Golden Gate Bridge Toll Plaza, San Francisco, CA.

If this schedule is met, the staff report will be sent by electronic mail to all Bidders on Friday, January 20, 2011.

If you have any questions, please do not hesitate to contact the DSO at (415) 923-2223.

Click here for a Detailed Breakdown of “Schedule of Prices.”

Click here for “List of Subcontractors” for the three apparent low bidders.