BID(S) RECEIVED

CONTRACT NO. 2012-BT-5
FUEL INJECTORS FOR DIESEL ENGINES

BID OPENING: Thursday, November 22, 2011, at 2:00 p.m.

Bids for the above-referenced Contract were received by the District Secretary’s Office (DSO) and publicly opened in the Board Room, Administration Building, Golden Gate Bridge Toll Plaza, San Francisco, CA, on Tuesday, November 22, 2011, at 2:00 p.m., listed in alphabetical order, as follows:

 

COMPANY

TOTAL

CATEGORY A

TOTAL

CATEGORY B

1.
BusWest, LLC
Fontana, CA
$93,709.05
$93,705.46*
$20,217.92
$20,217.91*
2. Cummins West, Inc.
San Leandro, CA
No Bid
$24,611.51
3. H.G. Makelim Company
South San Francisco, CA
$63,745.92
$17,264.78
4. Muncie Reclamation and Supply
dba Muncie Transit Supply
Muncie, IN
$58,319.18
$115,607.18*
$12,139.52
$17,835.77*
5. Performance Turbochargers, LLC
Fontana, CA
$78,494.98
$18,341.41
$20,313.93*

* Corrected price due to arithmetic error.

The Bids are currently under review by the District. Staff will prepare a written report that will include a recommendation. It is anticipated that the staff recommendation to award Contract No. 2012-BT-5, will be presented to the General Manager for approval the week of Monday, December 5, 2011. If this schedule is met, the District will notify the Bidders of staff’s recommendation by electronic mail or facsimile by Friday, December 9, 2011.

If you have any questions, please do not hesitate to contact the DSO at (415) 923-2223.

Click here for a Schedule of Prices.