March 25, 2004
(For Board: April 9, 2004)
REPORT OF THE BUILDING AND OPERATING COMMITTEE/
COMMITTEE OF THE WHOLE
Honorable Board of Directors
Golden Gate Bridge, Highway
and Transportation District
Honorable Members:
A meeting of the Building and Operating Committee was held in the Board
Room, Administration Building, Toll Plaza, San Francisco, California,
on Thursday, March 25, 2004, at 10:00 a.m., Chair Eddie presiding.
Committee Members Present (7): Chair Eddie; Vice Chair Reilly; Directors
Hernández, Martini, Middlebrook, Stroeh; President Smith (Ex Officio)
Committee Members Absent (2): Directors Ammiano and Boro
Other Directors Present (4): Directors Cochran, Harrison, Murray and Shahum
Committee of the Whole Members Present (11): Directors Cochran, Eddie,
Hernández, Martini, Murray, Reilly, Shahum and Stroeh; Second Vice
President Harrison; First Vice President Middlebrook; President Smith
Committee of the Whole Members Absent (7): Directors Ammiano, Boro, Brown,
Hall, Kerns, McGoldrick and Pahre
Staff Present: General Manager Celia G. Kupersmith; District Engineer
Denis J. Mulligan; Attorney David J. Miller; Deputy General Manager/Bridge
Division Kary H. Witt; Deputy General Manager/Bus Division Susan C. Chiaroni;
Deputy General Manager/Administration and Development Teri W. Mantony;
Deputy District Engineer Ewa Z. Bauer; Public Affairs Director Mary C.
Currie; Planning Director Alan R. Zahradnik; Acting Auditor-Controller/Budget
and Program Analysis Manager Jennifer Mennucci; Executive Assistant to
the General Manager Amorette Ko; Assistant Clerk of the Board Karen B.
Engbretson; Assistant Clerk of the Board, Trainee Patsy Whala
Visitors Present: José Luis Moscovich, Executive Director and Leroy
Saage, Project Manager for the Doyle Drive Environmental and Design Study
Project, San Francisco County Transportation Authority; Gary Kennerley,
Parsons Brinckerhoff; Patricia Vaughey, Doyle Drive Citizens Advisory
Committee
1. Presentation by the San Francisco County Transportation Authority
on the Doyle Drive Environmental and Design Study Project
Chair Eddie introduced José Luis Moscovich and Leroy Saage of the
San Francisco County Transportation Authority (SFCTA), who gave a PowerPoint
slide presentation on the status of the Doyle Drive Environmental and
Design Study Project (Doyle Drive Project). A copy of the presentation
is available in the Office of the Secretary of the District.
Mr. Moscovich stated that the progress SFCTA has achieved regarding the
Doyle Drive Project is due to the combined efforts of District staff,
various stakeholder agencies and the community. Mr. Saage provided a status
report of the Doyle Drive Project in regards to alternatives considered,
alternatives carried forward, design options and the current timeline.
He described the project implementation process, with Environmental Impact
Statement/Report preparation and review period occurring through the summer
of 2005, design taking place in 2006, construction beginning in 2008 and
the final project being completed in 2012.
Mr. Saage outlined the funding plan that has been approved by the California
Transportation Commission. A recent addition to the Doyle Drive Project
funding includes the allocation of $90 million due to the recent passage
of Proposition K, the City and County of San Franciscos one-half
cent transportation sales tax. Mr. Saage noted that SFCTA directs use
of the sales tax money and that the Metropolitan Transportation Commission
and the Federal Highway Administration would seek additional local contribution
from SFCTA in order to obtain matching federal funds.
Mr. Saage summarized the five project alternatives: (1) No-Build; (2)
Replace and Widen; (3) Long Tunnel; (4) Short Tunnel; and, (5) Presidio
Parkway. Mr. Saage continued with the presentation, describing in detail
the preliminary traffic analysis. He provided details of current traffic
conditions, a summary of the traffic analysis and how traffic would be
affected, including Golden Gate Transit and MUNI bus routes. He also pointed
out that all alternatives could provide wider lanes, median, shoulders
and new ramps and would accommodate expected traffic growth. Mr. Saage
emphasized the benefits of Alternative 5 (Presidio Parkway), such as fewer
historic structures displaced, less intrusive visual impact, smaller construction
footprint, shorter construction duration and lower cost. He further explained
the developmental stages of construction and the proposed traffic scenarios
regarding the Presidio Parkway option.
Discussion ensued among the Directors and the SFCTA representatives, including
the following salient points:
- Director Shahum inquired regarding potential impacts to Golden Gate Transit bus service. In response, Mr. Saage replied that overall, transit operations on Doyle Drive would be enhanced following completion of the project due to wider lanes and planned improvements to transit stops along Doyle Drive and at the Golden Gate Bridge Toll Plaza.
- Director Stroeh commended SFCTA for such an imaginative approach with the Presidio Parkway alternative, noting that a significant amount of time could have been saved if the Presidio Parkway concept had been developed earlier in the design development process.
Public Comment
Patricia Vaughey expressed her dissatisfaction with the traffic scenarios for the Doyle Drive Project, which propose diverting traffic exiting Doyle Drive from Marina Boulevard to Richardson Avenue and Lombard Street. She cautioned that when traffic on Lombard becomes congested, drivers often detour onto neighborhood streets such as Greenwich and Chestnut streets. She urged project planners to carefully identify potential traffic impacts to local streets in the Marina District when studying the environmental impacts of the Doyle Drive Project.
Action by the Board None Required
2. Authorize Actions
Relative to Award of Contract No. 2004-BT-8, San Rafael and Novato Bus
Facilities Pavement Rehabilitation, to Maggiora & Ghilotti, Inc.
In a memorandum to Committee, Deputy District Engineer Ewa Bauer, District
Engineer Denis Mulligan and General Manager Celia Kupersmith reported
on staffs recommendation for award of Contract No. 2004-BT-8, San
Rafael and Novato Bus Facilities Pavement Rehabilitation. The report stated
that severe settlement of the asphalt pavement at the San Rafael Bus Lot,
due to the heavy wheel loads of parked buses, requires removal of deteriorated
asphalt pavement and that significant deterioration of the Novato Bus
Facility employee parking lot requires an asphalt overlay to extend its
useful life.
The report stated that on March 16, 2004, three bids were received and
publicly read for Contract No. 2004-BT-8. The apparent low bidder is Maggiora
& Ghilotti, Inc., of San Rafael, with a bid price of $155,555. The
Engineers estimate for this project was $145,000. The report further
stated that the Engineering staff, the DBE Program Administrator and the
Attorney for the District have evaluated the bids and have determined
that the apparent low bid is responsive and responsible, and recommend
award of Contract No. 2004-BT-8, to Maggiora & Ghilotti, Inc. The
DBE Program Administrator has determined that Maggiora & Ghilotti,
Inc., has complied with the DBE requirements applicable to this contract.
Staff also recommends approval of a contract contingency in the amount
of $15,555, equal to 10% of the contract amount, and recommends approval
of a budget increase in the amount of $17,665, to be funded with a budget
transfer from the San Rafael Bus Facility Gas Tank Replacement project.
Staff recommended and the Committee concurred by motion made and seconded
by Directors STROEH/MARTINI to forward the following recommendation to
the Board of Directors for its consideration:
RECOMMENDATION
The Building and Operating Committee recommends that the Board of Directors
approve the following actions relative to Contract No. 2004-BT-8, San
Rafael and Novato Bus Facilities Pavement Rehabilitation:
a. Award Contract No. 2004-BT-8 to Maggiora & Ghilotti, Inc., San
Rafael, CA, in the amount of $155,555;
b. Authorize a contingency fund in the amount of $15,555, equal to 10%
of the contract award; and,
c. Authorize a budget increase in the amount of $17,665 to be funded with
a budget transfer from the San Rafael Bus Facility Gas Tank Replacement
project;
with the understanding that requisite funds are included in the Fiscal
Year 2004 Bus Division Capital Budget.
Action by the Board Resolution
NON-CONSENT CALENDAR
AYES (11): Directors Cochran,
Eddie, Hernández, Martini, Murray, Reilly, Shahum and Stroeh; Second
Vice President Harrison; First Vice President Middlebrook; President Smith
NOES (0): None
3. Authorize Increase for Change Order No. 47 to Contract No.
99-B-5, Golden Gate Bridge Seismic Retrofit Phase II South Approach
Structures, Relative to Repairs of Steel Elements of the Top and Bottom
Chords and Vertical Ribs of the Fort Point Arch
In a memorandum to Committee, Deputy District Engineer Ewa Bauer, District
Engineer Denis Mulligan and General Manager Celia Kupersmith reported
on the need to increase the amount of Change Order No. 47 to Contract
No. 99-B-5, Golden Gate Bridge Seismic Retrofit (Phase II), South Approach
Structures, by $143,000. This Change Order is for the repair of certain
steel elements of the Fort Point Arch. The report described the contract-specified
retrofit work on the Fort Point Arch associated with Contract No. 99-B-5,
including removing and replacing steel members, adding new steel plates
on top of existing members, and removing and replacing existing fasteners.
The report stated that the District investigated the condition of the
existing members and discovered that some of the existing elements of
the top and bottom chords and the vertical ribs, which are to receive
new steel plates, have lost significant amounts of steel material due
to corrosion so extensive that it prevents attachment of the new plates
to these existing members. In order to complete the retrofit at these
locations, the existing members must be repaired by removing deteriorated
steel and installing new structural steel pieces. In addition, the repair
will require cleaning and painting at the affected locations.
The Board of Directors, by Resolution No. 2003-113 at its November 21,
2003 meeting authorized the execution of Change Order No. 47 to begin
implementation of this structural steel repair and painting work. Since
then, however, additional locations have been found that require repairs
to complete the scope of this Change Order. Staff performed a cost analysis
for the total scope of work and negotiated a revised total price with
the Contractor for the expanded scope of repairs in the amount of $698,000.
Staff has determined that this amount is acceptable for the scope of work,
and recommends authorization of an increase in the amount of $143,000
for Change Order No. 47. The Federal Highway Administration has concurred
with this increase in cost. A copy of the report is available from the
Office of the Secretary of the District.
Staff recommended and the Committee concurred by motion made and seconded
by Directors STROEH/MARTINI to forward the following recommendation to
the Board of Directors for its consideration:
RECOMMENDATION
The Building and Operating Committee recommends that the Board of Directors
authorize an increase for Change Order No. 47 to Contract No. 99-B-5,
Golden Gate Bridge Seismic Retrofit (Phase II), South Approach Structures,
with Shimmick Construction Company, Inc./Obayashi Corporation JV, for
the repair of steel components of the Top and Bottom Chords and Vertical
Ribs of the Fort Point Arch, in the amount of $143,000, which increases
the cumulative amount of Contract Change Order No. 47 to $698,000; with
the understanding that requisite funds are available in the contract contingency
in the Fiscal Year 2004 Bridge Division Capital Budget.
Action by the Board Resolution
NON-CONSENT CALENDAR
AYES (11): Directors Cochran,
Eddie, Hernández, Martini, Murray, Reilly, Shahum and Stroeh; Second
Vice President Harrison; First Vice President Middlebrook; President Smith
NOES (0): None
4. Authorize Execution of a Change Order Nos. 67 and 80 to Contract
No. 99-B-5, Golden Gate Bridge Seismic Retrofit (Phase II), South Approach
Structures, for Painting the Towers and Bents of the South Approach Viaduct
and the Lower Truss of the Fort Point Arch
In a memorandum to Committee, Deputy District Engineer Ewa Bauer, District
Engineer Denis Mulligan and General Manager Celia Kupersmith reported
on the need for Change Order No. 67 and 80 to Contract No. 99-B-5, Golden
Gate Bridge Seismic Retrofit (Phase II), South Approach Structures, in
the amount of $667,100 and $2,500,000, respectively, relative to additional
painting of the Fort Point Arch. The report described the contract-specified
retrofit and painting work associated with Contract No. 99-B-5.
The report described the two
proposed Change Orders as follows:
1. Change Order No. 67, in the amount of $667,100, is for preparing the
steel surfaces and applying a topcoat finish of International Orange
to the three new towers and two new bents of the South Approach Viaduct;
and,
2. Change Order No. 80, in the amount of $2,500,000, is for preparing
the steel surfaces and applying a topcoat finish of International
Orange to a portion of the Fort Point Arch, specifically the retrofitted
members in the lower truss of the Fort Point Arch, which can be accessed
from the lowest level of the contractors work platforms.
The report also stated that relative to Change Order No. 67, the contractor
is required to sequentially remove the supporting towers and bents of
the Viaduct and replace them with new towers and bents fabricated and
top-coated with a gray prime coat in the shop. With this change order,
the contractor will apply the International Orange top coat
to the very visible elements of the Viaduct and therefore comply with
conditions of the Seismic Retrofit Projects environmental clearance.
The contractor provided a proposal cost of $13 per square foot for this
work, which is considerably below staffs estimated cost of $30
per square foot to perform this work under a separate contract.
The report further stated that relative to Change Order No. 80, the contractor
is required to remove and replace steel members, add new steel plates
on top of existing members, add new steel members and remove and replace
existing fasteners, approximately 74,240 square feet of surface area.
The report stated that the contract documents for Contract No. 99-B-5
did not include the application of an International Orange
topcoat of paint to the retrofitted steel structures of the Fort Point
Arch. The District decided to exclude the topcoat paint application to
allow time to determine which topcoat system would be compatible with
the existing paint and the specific prime paint systems used by the contractor.
The prime and topcoat paint systems have now been determined and the contractor
has provided the District with a price for topcoat painting at an average
of $34 per square foot. Staff has researched recent painting bid prices
for comparable large steel bridges in the Bay Area and has estimated a
cost of between $50 and $80 per square foot for performing this topcoat
painting work under a separate contract, due to the necessity of installing
a work access system exclusively for painting. The report further stated
that the work platforms installed as part of Contract No. 99-B-5 could
also be used for the topcoat painting work, avoiding the additional cost
of constructing special access for painting.
Staff recommends authorization of the above-described extra work to be
performed under these change orders to Contract No. 99-B-5, due to the
favorable prices for this work proposed by the contractor. The Federal
Highway Administration has concurred with staffs recommendation,
and grant funds received for the Phase II Seismic Retrofit project will
be used for this painting work. The District and the Contractor have agreed
to a compensable time extension of 45 calendar days that will change the
completion date from February 5 to March 22, 2005.
The report further stated that District staff is in the midst of negotiations
with the Phase II contractor, Shimmick Construction Company, Inc./Obayashi
Corporation JV, regarding additional work to repair and paint steel members
in the South Approach structures beyond these two change orders. It is
estimated, however, that the total price of this additional work will
exceed the remaining contingency for Contract No. 99-B-5. It is anticipated
that approval of these additional repairs will require an increase in
the Contract No. 99-B-5 contingency by a transfer of funds from the available
Phase III grant funds. Upon completion of negotiations with the contractor,
staff will present a recommendation for this funding transfer to the Committee
and Board for action. A copy of the report is available from the Office
of the Secretary of the District.
Staff recommended and the Committee concurred by motion made and seconded
by Directors STROEH/MARTINI to forward the following recommendation to
the Board of Directors for its consideration:
RECOMMENDATION
The Building and Operating Committee recommends that the Board of Directors
authorizes execution of Contract Change Orders to Contract No. 99-B-5,
Golden Gate Bridge Seismic Retrofit Phase II, South Approach Structures,
with Shimmick Construction Company, Inc./Obayashi Corporation JV, as follows:
1. Authorize execution of Contract Change Order No 67, for preparing the
steel surfaces and applying a top coat finish of International
Orange to the new supporting towers and bents of the South Approach
Viaduct, in the amount of $667,100; and,
2. Authorize execution of Contract Change Order No. 80, for preparing
the steel surfaces and applying a top coat finish of International
Orange to the retrofitted members in the lower truss of the Fort
Point Arch, in the amount of $2,500,000;
with the understanding that requisite funds are available in the contract
contingency in the Fiscal Year 2004 Bridge Division Capital Budget.
Action by the Board Resolution
NON-CONSENT CALENDAR
AYES (11): Directors Cochran,
Eddie, Hernández, Martini, Murray, Reilly, Shahum and Stroeh; Second
Vice President Harrison; First Vice President Middlebrook; President Smith
NOES (0): None
5. Status Report on Engineering Projects
In a memorandum to Committee, Deputy District Engineer Ewa Z. Bauer, District
Engineer Denis Mulligan and General Manager Celia Kupersmith reported
on current engineering projects. This report will be presented to the
Board of Directors at its meeting of March 26, 2004. A copy of the report
is available in the Office of the Secretary of the District.
Action by the Board None Required
6. Public Comment
Public comment was received relative to Agenda Item No. 1, Presentation
by the San Francisco County Transportation Authority on the Doyle Drive
Environmental and Design Study Project, as noted above.
7. Adjournment
All business having been concluded, the meeting was declared adjourned
at 11:05 a.m.
Respectfully submitted,
James C. Eddie, Chair
JCE:JST:PLW:plw
|
|