Updated May 16, 2013

REPAVING OF THE LARKSPUR FERRY TERMINAL PARKING LOT; ROLLING WEEKEND CLOSURES

Work Continues June 1-2- NO PARKING in Rows F thru P

The repaving of the Larkspur Ferry Terminal parking lot began in mid March. To minimize impact to ferry customers, the vast majority of the work is limited to weekends only and will take several months to complete.

Work continues the weekend of June 1/2. There is NO PARKING in rows F through P from 10pm Friday, May 31 through 5am Monday, June 3. Vehicles will be towed.

Rolling closures of several parking rows at a time will occur and the areas to be paved on a given weekend will be posted in advance of the weekend paving. There is no overnight parking in the areas designated for paving and vehicles will be towed accordingly.

The existing asphalt concrete surfacing at the Larkspur Ferry Terminal parking lot and perimeter road is in a deteriorated state and in need of repair. The existing interior parking lot asphalt concrete pavement and base material will be removed. This is followed by compaction of existing subgrade, installation of geotextile fabric, placement of new aggregate base, and placement and compaction of new 4-inch thick minimum hot mix asphalt pavement. At the Larkspur Terminal perimeter road, improvements include cold planing the existing surfacing and placing a 2-inch thick minimum hot mix asphalt pavement.

The project will also modify existing and construct new drainage facilities; install new pavement delineation and striping; remove and replace signage to meet the California Manual on Uniform Traffic Control Devices 2012 standards requirements, install new regulatory signs; and remove and replace existing pipe bollards and wheel stops.

The total project budget is $2.1 million with $1,704,000 in Federal Transit Administration grant funds (80%) and $426,000 District funds (20%).