REVISED December 18, 2006

--CLOSURE DATES REVISED--

TEMPORARY CLOSURE TO MERCHANT ROAD PLANNED

January 5 at 9 pm through January 8 at 5 am

Since August 2006, construction has been underway to realign Merchant Road (the exit to the right, immediately south of the Golden Gate Bridge toll plaza) with its connection to Lincoln Blvd. near the south end of the Golden Gate Bridge.

Merchant Road will be closed from 9 pm on Friday, January 5, 2007, through 5 am on Monday, January 8, 2007, to undertake paving of the newly realigned roadway.

The newly aligned portion of  Merchant Road will then open for the public at 5 am on Monday, January 8, 2007.


RAIN MAY DELAY THIS CLOSURE

WATCH FOR UPDATES