Golden Gate Bridge, Highway & Transportation District

Posted April 16, 2015

Golden Gate Bridge Toll Booth Seismic Retrofitting Complete

The seismic retrofitting of Golden Gate Bridge Toll Booths #3, #5, and #7 is now complete, and Toll Lanes #1 through #7 are all open, except at night from 7:00 p.m. to 5:00 a.m. when lanes are closed to allow the Toll Plaza roofing work to take place. Toll Booth #5 was completed on March 11, 2015, and Toll Booth #3 was completed on April 8, 2015.

The Toll Plaza clock was reinstalled on the night of April 10, 2015, but will not be placed back in service until the roofing work is complete and the final electrical connections are made, currently scheduled for May 2015.